Los Alamitos Trunk Sewer Construction Project – May 5, 2022
Post Date:05/05/2022 11:27 AM
Construction continues in the cities of Los Alamitos and Seal Beach. Work is currently being done at night when sewer flows are low.
Manhole Rehabilitation Work
Lexington Drive at Katella Ave. and northbound Los Alamitos Blvd. at Howard Ave.
Week of May 8th*
Nightwork, 8 p.m. – 6 a.m.
Pipe cleaning and grouting continues along southbound Los Alamitos Blvd. weeknights from 8 p.m. to 6 a.m.
*Dates and times are subject to change due to operational factors or inclement weather.
What to Expect:
Periodic traffic delays as a result of lane reductions and turn restrictions
Increased noise level
Lane closures
Certain bus stops along the route may be affected, please watch for posted signs and visit www.OCTA.net for details
As a reminder, this project is cleaning the existing sewer line, reinforcing the pipe joints with chemical grout, and repairing/rehabilitating/replacing the manholes. Further details about the project can be found in the fact sheet.