Rehabilitation of the Los Alamitos Trunk Sewer continues. Crews are busy completing repairing or replacing manholes and removing debris from the regional sewer line.
Upcoming Activities:
Oak Street
Construction activity on Oak Street is wrapping up this week ahead of the start of the school year. Final street restoration will take place on Saturday, August 13, and August 20.
Los Alamitos Blvd.
Manhole work is about to commence on southbound Los Alamitos Blvd. between Katella Ave. and Bradbury Rd. To properly prepare for this pipe cleaning will be done ahead of the manhole work. Pipe cleaning must be done at night when the sewer flows are low.
What to Expect:
*Dates and times are subject to change due to operational factors or inclement weather.
STAY IN THE KNOW
Sign up for text alerts
Sign up for e-notifications (Subscribe to “Los Alamitos” in the News section)
Questions? Construction Hotline 714.378.2965 or ConstructionHotline@ocsan.gov.
Project Description
OC San is rehabilitating two parallel sewers on north and southbound Seal Beach Blvd./ Los Alamitos Blvd., and along Katella Avenue, Oak Street, and Lexington Drive in the cities of Seal Beach and Los Alamitos. The work consists of removing calcium buildup at various pipe joints and injecting chemical grout to strengthen the pipe. Rehabilitation and/or replacement of over 70 manholes will also take place.
Sign up for the latest news and updates from the Orange County Sanitation District.