State College Sewer Construction – March 4, 2021

Home >> News >> State College Sewer Construction – March 4, 2021


For more information, please contact the Construction Hotline at (657) 208-7900 or via email at ConstructionHotline@ocsd.com

Visual progress is being made with the removal of K-rail from Vermont Ave. to South St. Final sewer pipe installations, lateral connections, and street restorations are continuing along State College Blvd. in Anaheim and Fullerton.

New activity:

State College Blvd. from Vermont Ave. to South St.

K-rail has been lifted along State College Blvd. from Vermont Ave. to South St. Restoration of State College Blvd. is in progress and will continue into late Spring 2021*. Occasional lane reductions and traffic control may be necessary.

Current activities:

State College Blvd. and Romneya Dr. Intersection

Due to construction sequencing, connection of the local sewer to newly installed regional sewer line will be on hold until the end of March. Occasional daytime shoring activity will occur. Day and nighttime work will resume end of March during the hours reflected below:

  • Ongoing – April 2021*
  • Days 8:30 a.m. – 3:30 p.m. and Nights 8 p.m. – 6 a.m.
  • Left turn restrictions as necessary

State College Blvd. and Orangethorpe Ave. (City of Fullerton)

Sewer Line Connection – In 2017 three miles of sewer pipe was installed on State College Blvd. in the City of Fullerton.  Now that the sewer has been installed in the City of Anaheim, we need to return to connect the two pipes. A small section of pipe will need to be installed to join the two pipes.

  • Ongoing – May 2021*
  • Monday – Friday 7 a.m. – 7 p.m., occasional Saturdays
  • Traffic may be reduced to one travel lane in each direction
  • Northbound OCTA bus route will be temporarily relocated
  • See NOTICE for details

State College Blvd. and La Palma Ave. Intersection

Sewer installation across the La Palma Avenue intersection, connection of the local sewer line to the regional sewer line, and miscellaneous activities including street restoration.

  • Ongoing – May 2021*
  • Monday – Saturday 8:30 a.m. – 3:30 p.m. and 8 p.m. – 6 a.m.
  • Left turn restrictions, U-Turns can be made at the next intersection
  • See NOTICE for details

Vermont Avenue to Underhill Avenue – restoration

 Activities continues in this area with removal of shoring, connection of laterals to the main sewer pipe, and complete street restoration.

  • Ongoing – Spring/Summer 2021*
  • Monday – Friday, 7 a.m. to 5 p.m. , occasional Saturdays
  • Traffic impacts consist of lane reductions and left turn restrictions

We encourage you to use alternate routes and allow extra time to reach your destination. Please use caution when traveling in the traffic zones.

We thank you for your continued patience as we work to improve Orange County’s infrastructure. To learn more about this project visit www.ocsan.gov/StateCollege.

*Dates are subject to change due to operational factors or inclement weather.

Project Description:

The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction began in late summer 2018 and is scheduled to be completed in spring 2021.  Once the project is complete, eight million gallons of wastewater will be diverted to OCSD’s Plant No. 1 in Fountain Valley for treatment before being sent to the Groundwater Replenishment System.   This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.