For more information, please contact the Construction Hotline at (657) 208-7900 or via email at ConstructionHotline@ocsan.gov
The State College Sewer Construction project has replaced four miles of regional sewer pipe on State College Blvd. in Anaheim from the 91 freeway to Orangewood Avenue. Three miles have also been installed in the City of Fullerton from Yorba Linda Blvd. to the 91 freeway.
Current Activity:
Craig Regional Park
Minor construction work is required at various manholes within Craig Regional Park to restrict the infiltration of groundwater into the regional sewer pipe.
-
- March 15th, 2021 lasting approximately 2 weeks*
- Work Hours – 10:00 p.m. to 8:00 a.m.
- See NOTICE for details
State College Blvd. from Vermont Ave. to South St.
K-rail has been lifted along State College Blvd. from Vermont Ave. to South St. Restoration of State College Blvd. is in progress and will continue between Vermont Ave. and Underhill Ave. into late spring/early summer 2021*. Occasional lane reductions and traffic control may be necessary.
State College Blvd. and Romneya Dr. Intersection
Due to construction sequencing, connection of the local sewer to newly installed regional sewer line will be on hold until the end of March. Occasional daytime shoring activity will occur.
- March – April 2021*
- 8:30 a.m. – 3:30 p.m.
- Left turn restrictions as necessary
- Complete street restoration will be done in the summer.
State College Blvd. and La Palma Ave. Intersection
Sewer installation across the La Palma Avenue intersection, connection of the local sewer line to the regional sewer line, and miscellaneous activities including street restoration.
- Ongoing – May 2021*
- Monday – Saturday 8:30 a.m. – 3:30 p.m. and 8 p.m. – 6 a.m.
- Left turn restrictions, U-Turns can be made at the next intersection
- See NOTICE for details
- Complete street restoration will be done in the summer.
State College Blvd. and Orangethorpe Ave. (City of Fullerton)
Sewer Line Connection – In 2017 three miles of sewer pipe was installed on State College Blvd. in the City of Fullerton. Now that the sewer has been installed in the City of Anaheim, we need to return to connect the two pipes. A small section of pipe will need to be installed to join the two pipes.
- Ongoing – May 2021*
- Monday – Friday 7 a.m. – 7 p.m., occasional Saturdays
- Traffic may be reduced to one travel lane in each direction
- Northbound OCTA bus route will be temporarily relocated
- See NOTICE for details
We encourage you to use alternate routes and allow extra time to reach your destination. Please use caution when traveling in the traffic zones.
We thank you for your continued patience as we work to improve Orange County’s infrastructure. To learn more about this project visit www.ocsan.gov/StateCollege.
*Dates are subject to change due to operational factors or inclement weather.
Project Description:
The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction began in late summer 2018 and is scheduled to be completed in spring 2021. Once the project is complete, eight million gallons of wastewater will be diverted to OC San’s Plant No. 1 in Fountain Valley for treatment before being sent to the Groundwater Replenishment System. This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.