Upcoming Work

LOCATION:  Airway Ave. between Baker St. and McCormick Ave.

  • What: Pipeline rehabilitation by lining the pipe
  • When:  Anticipated to occur in the coming weeks
  • Work Hours: This operation will require 24/7 continuous work.

More information will be provided as dates and details are confirmed. 

 

2024.02 Baker to Airport Loop

Current Work

 

LOCATION:  Airway Ave. between Baker St. and McCormick Ave.

Excavation of three access pits is complete and currently covered with steel plates. Crews are working on restriping the street back to its original configuration. K-rail and cones have been relocated to the next segment of activity.

See above for upcoming work in the area.

 

AP 2 Street View North

January 2024 – K-rail, cones, and signage at an access pit during excavation on Airway Drive.

LOCATION:  Airway Ave., east of McCormick Ave., and onto Airport Loop Dr.

  • What: Excavation of access pits located several hundred feet apart
  • When:  Ongoing and lasting approximately 2 months
  • Work Hours: 7 a.m. – 7 p.m., Monday – Friday

Impacts

  • Travel lanes reconfigured with reduced street parking.
  • Increased noise due to construction activity.
  • A lane of travel in each direction will remain.
  • Please drive with caution with the new street striping layout.

*All dates and times are subject to change due to operational factors or inclement weather.

Project Description

This project will rehabilitate two parallel regional sewer pipelines, along a 1-mile stretch on Airway Avenue and Airport Loop Drive in the City of Costa Mesa, near the John Wayne Airport. The rehabilitation of the two pipelines must occur one at a time and will take place in separate phases.

Project elements also include improvements at the Main Street Pump Station.  See map below (blue line).

 

 

 

Airway Airport Loop

Construction Schedule

Project Phase Schedule

Keep Informed

Sign up for e-notifications to stay informed about this project by subscribing and selecting the “Airway-Airport Loop Sewer” subscription topic.

Sign up for text notifications here and selecting “Airway Airport Loop” under groups.

www.ocsan.gov/airwayairport

Other Information

For information about a nearby project in the City of Costa Mesa, please visit Costa Mesa Sewer Rehabilitation along I-405 Project.