Upcoming Driveway Closure for Tustin Business Park

Home >> News >> Upcoming Driveway Closure for Tustin Business Park
Construction Alert

Updated 10/24/17 – Northbound Red Hill Avenue between Valencia Avenue and Edinger Avenue will be down to 1 lane until 6 p.m.  Construction activity will continue on Wednesday, October 25.

The driveway to the Tustin Business Park located at Red Hill Avenue and Parkway Loop will be temporarily closed Tuesday, October 24, 6 a.m. – 5 p.m.  Dates and times are subject to change due to unforeseen operational factors or inclement weather.  Please use other driveways when the closure is in place.

 

 

 

A section of an existing waterline crossing over the new sewer pipeline will be replaced.  There will be no interruption to water or sewer service.  Please see the construction alert for more information.

Northbound Red Hill Avenue will be down to one lane when this work is taking place.

Project Completed 

Back in September, construction wrapped up on the Red Hill Sewer Improvements Project.  Crews are focusing on the very last few items to officially complete the project.  Some items include landscaping and replacement of a section of waterline by Red Hill Avenue and Parkway Loop/Industrial Drive (see the latest construction alert and information above).

We want to give a big thank you to the community for showing us patience and understanding during construction.  We understand it is never easy for those who live, work or commute in the area.

The photo below shows a portion of the construction work that took place at the intersection of Red Hill Avenue and Mitchell Avenue over the summer.  It’s hard to imagine that the roadway looked like this only a few months ago.

 

Project Overview

The project replaced and rehabilitated portions of the Red Hill Sewer System which consists of two parallel sewer pipelines.  The original sewer system was constructed in the early 1960’s and 1970’s.

  • The construction began May 2016 and was completed in about 18 months.
  • Installed nearly one mile of 30- to 33-inch diameter sewer pipeline, more than 20-feet below the roadway, along Red Hill Avenue between Warner Avenue and Edinger Avenue using open cut trench excavation.
  • Rehabilitated approximately 1.5 miles of existing pipeline, ranging in sizes between 21- and 36-inch diameter pipeline, along Red Hill Avenue between McGaw Avenue and Walnut Avenue using the trenchless cured-in-place pipe construction method.
  • Construction of 17 manholes ranging from 60- to 96-inch in diameter.
  • Rehabilitation of 50 manholes.
  • Sewer repairs of existing sewer system at the intersection of Mitchell Avenue and Newport Avenue by open cut trench excavation.
  • Sewer repairs of existing sewer system at the intersection of Mitchell Avenue and Red Hill Avenue by open cut trench excavation.

 

Questions?

If you have any questions or want the most up-to-date information, please call our Construction Hotline at (714) 378-2965 or e-mail constructionhotline@ocsd.com.

______________________________________________________________________ 

Project Description:

This project will replace and/or rehabilitate portions of the Red Hill Sewer System which consists of two parallel sewer pipelines within the cities of Tustin, Irvine, and Santa Ana.  Construction began May 2016 and lasts approximately 18 months.


www.ocsd.com/redhill