State College Sewer Construction Update – November 12, 2019

Home >> News >> State College Sewer Construction Update – November 12, 2019

State College Sewer Construction Update – November 12, 2019

Installing a 54-inch diameter sewer pipeline, 20 feet below the ground on a very busy arterial road is no easy task. There are other utilities, space, traffic, and above all, people to consider as you’re attempting to complete the installation. The construction project on State College Blvd. in Anaheim is this exact scenario. A new sewer line needs to be installed along four miles of the road which means there are many simultaneous moving parts. Take a look at our current work efforts along State College.

Platinum Triangle (Artisan to Gateway) – NEW WORK HOURS

  • Construction work is switching from nights to days. New hours are: Monday – Friday,
    7 a.m. – 5:30 p.m.
  • No left hand turns onto Gene Autry. East/west traffic on Gene Autry will not be able to cross State College Blvd. during these hours.

Platinum Triangle (Orangewood) – NEW WORK HOURS

  • Construction work is switching from nights to days. New hours are: Monday – Friday,
    5 a.m. – 7 p.m.

    Ongoing – March 2020
  • Lane reductions and turn restrictions are necessary. Current work consist of connecting laterals to the new line so service is not interrupted once the new line is put into service.  Manholes need to be installed to make the connections which requires excavation. When we excavate, we need to install shoring, which is steel sheeting that reinforces the soil in the excavated area. This activity will cause some minor vibration.

night wk OW

Cerritos Avenue to Ball Road

  • Nightwork: Monday – Friday, 8 p.m. – 6 a.m.
  • Ongoing – December 2020
  • Current work consist of connecting laterals to the new line so service is not interrupted once the new line is put into service. Lane reductions will be in place.

Ball Road to Vermont Avenue

  • Monday – Friday, occasional Saturdays. 7 p.m. – 7 p.m. (Nightwork will be required at times, notices will posted as dates become available).
  • Ongoing – November
  • Sewer installation is complete. Street, landscaping, and irrigation are being restored. Left turns may be restricted as this work occurs.

SR-91 to La Palma Avenue

  • Monday – Friday, occasional Saturdays. 7 a.m. – 7 p.m.  (Nightwork will be required at times. Notices will be posted as dates become available).
  • Ongoing – December 2019
  • Sewer installation – this requires demo, potholing for utilities, excavation,  shoring, laying pipe, backfilling, constructing manhole, etc. Work requires lane reduction and turn restrictions.

manhole install_2019

We have a new Neighborhood Bulletin, an informational newsletter about the project, for the community by the 91 freeway, and its is also available in Spanish. Take a look at the latest  progress map for the overall project schedule.

For questions please contact our Construction Hotline at 657.208.7900 or via email at ConstructionHotline@ocsd.com.   

We understand construction can be an inconvenience, we apologize in advance and appreciate your patience as we work to improve our infrastructure.

*Dates are subject to change due to operational factors or inclement weather.

_____________________________________________________________________

Project Description:
The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction began in late summer 2018 and is scheduled to be completed in 2020.  Once the project is complete, eight million gallons of wastewater will be diverted to OCSD’s Plant No. 1 in Fountain Valley for treatment before being send to the Groundwater Replenishment System.  This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.