State College Sewer Construction Update – January 6, 2021

Home >> News >> State College Sewer Construction Update – January 6, 2021

For more information please contact the Construction Hotline at (657) 208-7900 or via email at ConstructionHotline@ocsd.com  Happy New Year! As we start 2021, we are at the tail end of this project, 99.5 percent of the sewer pipe is in the ground with only 150 feet of pipe left to be installed!Take a look at the ongoing activities:State College Blvd. at Westport Drive – Detour

The local sewer must be connected to the newly installed regional sewer. To do this Westport Drive between State College and Reseda St. will be blocked off restricting parking. Access to and from Westport Drive will be restricted. A detour will be in place as the work takes place.

  • Ongoing – lasting until approximately Mid-February 2021*
  • Monday – Saturday, 7 a.m. – 7 p.m.
  • See NOTICE for details and detour map

Vermont Avenue to Underhill Avenue 

Construction continues in this area with removal of shoring, connection of laterals to the main sewer pipe, and complete street restoration.

  • Ongoing – Spring 2021*
  • Monday – Friday, 7 a.m. to 5 p.m. – Occasional Saturday’s
  • Traffic impacts consist of lane reductions and left turn restrictions

State College Blvd. and La Palma Ave. Intersection

Sewer installation across the La Palma Avenue intersection, connection of the local sewer line to the regional sewer line, and miscellaneous activities including street restoration.

  • Ongoing – February 2021*
  • Monday – Saturday 8:30 a.m. – 3:30 p.m. and 8 p.m. – 6 a.m.
  • Left turn restrictions, U-Turns can be made at the next intersection

Future Scheduled Construction Activities:

State College Blvd. and Orangethorpe Ave. (City of Fullerton)

Sewer Line Connection – In 2017 three miles of sewer pipe was installed on State College Blvd. in the City of Fullerton.  Now that the sewer has been installed in the City of Anaheim, we need to return to connect the two pipes.

  • As early as January 25, 2021 – April 2021*
  • Monday – Friday 7 a.m. – 7 p.m.
  • More details to follow.

We encourage you to use alternate routes and allow extra time to reach your destination. Please use caution when traveling in the traffic zones.

We thank you for your continues patience as we work to improve Orange County’s infrastructure. To learn more about this project visit www.ocsd.com/StateCollege.

*Dates are subject to change due to operational factors or inclement weather.

Project Description:

The project is replacing four miles of sewer along State College Boulevard from the SR-91 to Orangewood Avenue in the City of Anaheim. Construction began in late summer 2018 and is scheduled to be completed in spring 2021.  Once the project is complete, eight million gallons of wastewater will be diverted to OCSD’s Plant No. 1 in Fountain Valley for treatment before being sent to the Groundwater Replenishment System.   This is Phase B of a two-phase project; Phase A was completed in 2017 and took place from Yorba Linda Blvd. to SR-91 in the City of Fullerton.