Cypress Trunk Sewer

Home >> Construction >> Cypress Trunk Sewer

Cypress Trunk Sewer

Preparation work for the Cypress Trunk Sewer Project continues as part of major improvements to the regional sewer system throughout Cypress, La Palma, and Los Alamitos.

For the next few weeks, potholing and exploratory work will be done along the project alignment. This work involves carefully excavating holes to locate and verify underground utilities, as well as accessing manholes for upcoming rehabilitation work. After this work is complete, pipeline cleaning, grouting, and manhole rehabilitation will take place.

Here’s what you need to know about the upcoming work:

Location: Along the project alignment in Cypress, La Palma, and Los Alamitos (see map)

  • When: Ongoing and lasting until the end of August 2025*
    • Crews will be at each location for 1-4 days*
  • Hours: Monday-Friday, 8:30 a.m. – 4:30 p.m.*
  • Impacts:
    • Reduced traffic lanes
    • Traffic control while work is being performed
    • Increased activity, dust, and noise levels

Heads up, school-goers! Preparation work is scheduled near Clara J. King Elementary School and Steve Luther Elementary School later this month. There will always be thru street access going north and south on Moody Street and east and west on La Palma Avenue.

  • Clara J King Elementary School: Work starting as early as August 18, lasting 3-4 days*
  • Steve Luther Elementary School: Work starting as early as August 25, lasting approximately one week*

Please ensure that you follow all posted traffic signs for your safety and the safety of our crews.

 *All dates and times are subject to change due to operational factors or inclement weather.

Project Description:

The regional sewer line in the cities of Cypress, Los Alamitos, and La Palma is approximately 50 years old and in need of upgrades. The Cypress Trunk Sewer Project will focus on enhancing about 7 miles of sewer, replacing portions of the pipe with larger diameter pipe to increase the capacity, or rehabilitating other segments of pipe to extend the life of the sewer system. Approximately 100 manholes will also be replaced and/or rehabilitated. These repairs will extend the life of the sewer pipes by another 50 years.

Schedule:
Construction is anticipated to begin in Summer 2025 and last approximately 3 years.

Project Location

Stay In The Know

Community Liaison:
(714) 378-2965

Email:
constructionhotline@ocsan.gov

Sign up for text alerts:
click here

Site Location

Construction Schedule

2025-2028

Construction Budget

$29 million