Construction continues on Orange Avenue in the City of Anaheim for the Orange Western Trunk Sewer Project. Sewer line repair and manhole replacement work is underway.
- When: Ongoing – through summer 2022*
- Where: Orange Ave. between Danbrook Ave. and Western Ave.
- Work hours:
- Monday – Friday, 7 a.m. – 9 p.m., Saturday – 8 a.m. – 8 p.m.
- Nightwork is sporadically required as some activities need low sewer flows in the pipe.
- Lane reductions are necessary to allow enough space to perform the work. This may impact parking access.
Upcoming Work Area
*Dates and times are subject to change due to operational factors or inclement weather.
What to Expect:
- Periodic traffic delays because of lane reductions and turn restrictions
- Increased noise level
- Certain bus stops along the route may be affected, please watch for posted signs and visit www.OCTA.net for details
Overall Project Timeline: Winter 2022 –Winter 2023
For overall project details read the project Fact Sheet.
STAY IN THE KNOW
Sign up for text alerts
Project Description
Manholes and sections of sewer pipeline on Western Avenue and Orange Avenue in the Cities of Buena Park, Anaheim, and Cypress will be rehabilitated to extend their service life. OC San will clean and inject chemical grout into the pipelines and rehabilitate or replace manholes along the highlighted section of the entire project area map. Small segments of pipe will also be replaced.