Los Alamitos Trunk Sewer Project – December 7, 2022

Home >> News >> Los Alamitos Trunk Sewer Project – December 7, 2022

Los Alamitos Trunk Sewer Project banner  Manhole repair work is taking place on three manholes on the intersection of Los Alamitos Blvd. and Katella Ave. in the City of Los Alamitos. This work is occurring at night when sewer flows are lowers and to minimize impact to local businesses and commuters. This rehabilitation work will extend the life of the regional sewer system.

City of Los Alamitos

Intersection of Los Alamitos Blvd. and Katella Ave.

    • When: Week of Dec. 5 – January 2023*
    • Work Hours: Monday – Friday, 8 p.m. – 6 a.m.
    • Impacts:
      • Periodic traffic delays due to lane reductions and turn restrictions
      • Increased noise level
      • Potential dust
      • Access to all properties will be maintained
      • Cross walks may be closed intermittently

 

Los Alamitos Blvd. between Hedwig Rd. and Bradbury Rd.

  • When: December 1 – end of December 2022*
  • Where: Southbound lanes of Los Alamitos Blvd.
  • Work Hours: Monday – Friday, 8:30 a.m. – 5 p.m.
  • Impacts: Periodic traffic delays due to lane reductions and turn restrictions.

Please allow extra time when traveling in this area.

*Dates and times are subject to change due to operational factors or inclement weather.

STAY IN THE KNOW

Sign up for text alerts

Sign up for e-notifications (Subscribe to “Los Alamitos” in the News section)

Questions?  Construction Hotline 714.378.2965 or ConstructionHotline@ocsan.gov.

Project fact sheet.

 Project Description

OC San is rehabilitating two parallel sewers on north and southbound Seal Beach Blvd./ Los Alamitos Blvd., and along Katella Avenue, Oak Street, and Lexington Drive in the cities of Seal Beach and Los Alamitos. The work consists of removing calcium buildup at various pipe joints and injecting chemical grout to strengthen the pipe. Rehabilitation and/or replacement of over 70 manholes will also take place.

Construction area map