LOCATION: Western Ave. between Tyler Ave. to Del Monte Dr.

Construction continues on the rehabilitation of the regional sewer pipe on Western Ave. This activity requires excavation, shoring installation, and dewatering to safely perform the work. A bypass system is also necessary to reroute the sewer to maintain uninterrupted sewer service to the community. This operation is complex which prolongs the amount of time needed to perform the work. Consecutive day and night work will be necessary for a portion of the schedule to complete the work.

Night Work

  • When: Week of 9/18 – End of October 2023*
  • Work Hours: Monday – Friday; 7 p.m. – 5 a.m.

Day Work

  • When: Ongoing – Fall 2023*
  • Work Hours: Monday – Friday; 8 a.m. – 9 p.m., Occasional Saturdays

Impacts:

  • Lane reductions and turn restrictions
  • Parking restrictions
  • Noise and dust
  • Permanent traffic control until work is completed
  • For bus stop information please visit www.octa.net.

LOCATION: Orange Avenue between Knott Ave and Western Ave.

The sewer pipe is being replaced along a portion of Orange Ave. Bypass pumps are required to reroute the sewer flow to allow for the repair to be completed without interrupting service to the community. This specific activity requires the use of both permanent and temporary traffic control to successfully complete the work. This will reduce traffic lanes and impact street parking until the work is completed.

  • When: Ongoing – October 2023*
  • Work Hours: Monday – Friday, 9 a.m. – 9 p.m.
  • Impacts: Lane reductions and parking restrictions.

LOCATION: Orange Avenue at Knott Ave. and Western Ave.

OC San’s regional sewer project on Orange Ave. is wrapping up. One of the last phases is paving which will occur over a two-day period along Orange Ave.  To minimize the impact on the community OC San will be taking advantage of the student-free day on Monday, October 9 to pave the area by the high school.

North and southbound travel on Western Ave. and Knott Ave. will be restricted at Orange Ave. based on its respective workday as noted on maps. East/west crosswalks will also be restricted during this time. Detours will be in place, please monitor signage carefully and utilize alternate routes to reach your destination.

Timeline:

  • When and Where:
    • Monday, October 9: Intersection of Orange Ave. and Western Ave.
    • Tuesday, October 10: Intersection of Orange Ave. and Knott Ave.
  • Work Hours: 8:30 a.m. – 5:30 p.m.*

Day 1: Monday, October 9: Intersection of Orange Ave. and Western Ave.

Day 2: Tuesday, October 10: Intersection of Orange Ave. and Knott Ave.

 

City of Cypress

LOCATION: Orange Ave. between Valley View St. and Holder St.

Work in the City of Cypress is close to being complete. The final phase requires slurry seal to be placed along a portion of the road along Orange Ave. Due to nature of the work and material, there will be no parking along the work area until everything is completed.

  • When: September 28 – September 30*
  • Work Hours: Thursday – Saturday, 8:30 a.m. – 9 p.m.
  • Impacts: Lane reductions and parking restrictions along work area.

For your safety and that of our crew, please follow all posted traffic signs and use caution while driving in the construction zone,

 *Dates and times are subject to change due to operational factors or inclement weather.

Overall Project Timeline:  Winter 2022 – Fall 2023*

For overall project details read the project Fact Sheet. 

STAY IN THE KNOW

Sign up for text alerts

Sign up for e-notifications (Subscribe to “Orange Western” in the News section)

Questions?  Construction Hotline 714.378.2965 or ConstructionHotline@ocsan.gov.

Project Description

Manholes and sections of sewer pipeline on Western Avenue and Orange Avenue in the Cities of Buena Park, Anaheim, and Cypress will be rehabilitated to extend their service life. OC San will clean and inject chemical grout into the pipelines and rehabilitate or replace manholes along the highlighted section of the entire project area map. Small segments of pipe will also be replaced. 